January 28, 2023 (Saturday)
From 6:00 AM to 6:00 PM
Affected Areas:
Entire Municipality of Bunawan, Trento, Sta. Josefa, and Veruela
Activities Undertaken (NGCP):
- P&E request to facilitate the swinging of Bislig-Baganga 69kVL to its new 69kV feeder. Commissioning of new HVE.
- P&E to undertake Bislig-Baganga 69kVL feeder protection revamping.
- Undertake troubleshooting of the 69kV bus no. 2 protection signals to Transformer protection and conduct trip simulations.
- *Implementation of Mindanao Substations Upgrading Project.
- Energization of the upgraded Barobo Substation of SURSECO I.